| NEWS |
News from Clement Yacht Harbour Systems
|
Marinas Emirates Palace Hotel Marina - vom 14.12.2010, 10:04 | KG |
|---|
|
The structural works of the additional mega yacht berth with a length of more than 135 m and a pontoon width of 8 m have been completed. Hence, even now mega yachts with a length of 100 m and longer can be moored at this berth. At the moment the final MEP works for the provision of the enormous power - and water requirement are being in progress.

| | |
Floating Platforms Floating Art Object VINETA at its final location on the Lake Stoermthal - vom 02.12.2010, 12:56 | KG |
|---|
|
The floating art object „VINETA“(construction of a church on CLEMENT’s floating foundation) was anchored at its final location on the Lake Stoermthal on 24 November 2010.
The overall construction has a weight if 330 tons; the floating foundation is 20 m long and 15 m wide. It has a freeboard of 1.20 m.
The floating foundation has been made of 5 single elements casted to a rigid platform using connection beams as ring foundation. After completion of the building construction on the floating foundation, the construction had been floated with progressive flooding of the lake and was finally towed to the final location from the construction site to the present location after final state of construction.

| | |
Marinas Marina Muecheln - vom 26.10.2010, 08:45 | KG |
|---|
|
From 4 to 19 October 2010 seven floating breakwater as well as 10 floating pontoons were installed and anchored in the future marina Muecheln on the lake Geiseltal. The equipment of this facility will be carried out before the water sports and boat season in spring 2011. Until then the flooding of this former mining lake will be completed as well. In the first extension phase the facility will accommodate 70 boats.

| | |
Floating Platforms Completion of the maintenance berth in Kleinzschachnitz / Dresden - vom 08.07.2010, 10:48 | KG |
|---|
|
The new maintenance berth for the inland water transport of the Dresden Transport Authority was put into operation in Kleinzschachnitz (Dresden) in June 2010. The floating concrete pontoon with a surface of 60 sqm is only anchored on a pier anchor as well as on the access bridge.The pontoon is equipped with service pedestals for the supply of fresh water and power for the ships.

| | |
Marinas Completion of the marina (BUGA) in Schwerin - vom 02.07.2010, 11:25 | KG |
|---|
|
After deconstruction of the sea crossing, the removal of the large pontoons and the carriage overland to a new location, the extra-prepared and remaining floating concrete pontoons of the former sailing club Schwerin in the area of the crossing have been installed and brought to a higher standard compared to the previously existing marina made of driven wooden construction. Since June 2010 the marina has been operating with about 100 berths.

| | |